[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117118":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117118,789,1,"单选题","若施工作业所能依据的定额齐全，则在编制施工作业计划时宜采用的定额是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","概算指标",false,{"key":16,"text":17,"correct":14},"B","概算定额",{"key":19,"text":20,"correct":14},"C","预算定额",{"key":22,"text":23,"correct":24},"D","施工定额",true,"施工定额是以同一性质的施工过程一工序，作为研究对象，表示生产产品数量与时间消耗综合关系编制的定额。施工定额属于企业定额的性质。施工定额是工程建设定额中分项最细、定额子目最多的一种定额，也是建设工程定额中的基础性定额。施工定额由人工定额、材料消耗定额和机械台班使用定额所组成。施工定额直接应用于施工项目的施工管理，用来编制施工作业计划、签发施工任务单、签发限额领料单，以及结算计件工资或计量奖励工资等。施工定额也是编制预算定额的基础。考前黑钻押题，金考典软件考前更新，下载链接 www.jinkaodian.com",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]