[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117113":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117113,789,1,"单选题","某出料容量0.5m3的混凝土搅拌机，每一次循环中，装料、搅拌、卸料、中断需要的时间分别为1、3、1、1 分钟，机械利用系数为0.8，则该搅拌机的台班产量定额是（）m3\u002F台班。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","32",true,{"key":16,"text":17,"correct":18},"B","36",false,{"key":20,"text":21,"correct":18},"C","40",{"key":23,"text":24,"correct":18},"D","50","施工机械台班使用定额的编制。1+3+1+1=6分钟，60\u002F6=10次，一个台班是8小时，台班产量定额=10*.5*8*0.8=32m3\u002F台班。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]