[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117096":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117096,789,1,"单选题","根据《建设工程工程量清单计价规范》暂列金额可用于支付（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工中发生设计变更增加的费用",true,{"key":16,"text":17,"correct":18},"B","业主提供了暂估价的材料采购费用",false,{"key":20,"text":21,"correct":18},"C","因承包人原因导致隐蔽工程质量不合格的返工费用",{"key":23,"text":24,"correct":18},"D","因施工缺陷造成的工程维修费用","暂列金额尚未确定或者不可预见的所需材料、工程设备、服务的采购，施工中可能发生的工程变更、合同约定调整因素出现时的工程价款调整以及发生的索赔、现场签证确认等的费用。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]