[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117070":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117070,789,1,"单选题","根据《建设工程项目管理规范》，建设工程施工前由施工企业法定代表人或其授权人与项目经理协商制定的文件是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工组织设计",false,{"key":16,"text":17,"correct":18},"B","项目管理目标责任书",true,{"key":20,"text":21,"correct":14},"C","施工总体规划",{"key":23,"text":24,"correct":14},"D","工程总承包合同","项目管理目标责任书应在项目实施之前，由法定代表人或其授权人与项目经理协商制定。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]