[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117069":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117069,789,1,"单选题","根据《建设工程施工合同（示范文本）》，项目经理在紧急情况下有权采取必要措施保证与工程有关的人身，财产和工程安全，但应在48 小时内向（ ）提交书面报告。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包方法定代表人和总监理工程师",false,{"key":16,"text":17,"correct":18},"B","发包方代表和总监理工程师",true,{"key":20,"text":21,"correct":14},"C","监督只能部门和承包方法定代表人",{"key":23,"text":24,"correct":14},"D","政府只能监督部门和发包人代表","在紧急情况下为确保施工安全和人员安全，在无法与发包人代表和总监理工程师及时取得联系时，项目经理有权采取必要的措施保证与工程有关的人身、财产和工程的安全，但应在48 小时内向发包人代表和总监理工程师提交书面报告。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]