[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117068":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117068,789,1,"单选题","下列建设工程项目目标动态控制的工作中，属于准备工作的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","收集项目目标的实际值",false,{"key":16,"text":17,"correct":18},"B","对项目目标进行分解",true,{"key":20,"text":21,"correct":14},"C","将项目目标的实际值和计划值相比较",{"key":23,"text":24,"correct":14},"D","对产生偏差采取纠偏措施","项目目标动态控制的准备工作：将对项目的目标进行分解，以确定用于目标控制的计划值。黑钻押题，请用金考典考试软件 ,考前免费更新 www.jinkaodian.com @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]