[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117066":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117066,789,1,"单选题","大型建设工程项目进度目标分解的工作有1.编制各子项目施工进度的计划；2.编制施工总进度计划；3.编制施工总进度规划；4.编制项目各子系统计划、正确的目标分解过程是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2-3-1-4",false,{"key":16,"text":17,"correct":14},"B","2-3-4-1",{"key":19,"text":20,"correct":21},"C","3-2-1-4",true,{"key":23,"text":24,"correct":14},"D","3-2-4-1","对于大型建设工程项目，应通过编制施工总进度规划、施工总进度计划、项目各子系统和各子项目施工进度计划等进行项目施工进度目标的逐层分解。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]