[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117065":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117065,789,1,"单选题","项目部针对施工进度滞后问题，提出了落实管理人员责任，优化工作流程、改进施工方法、强化奖惩机制等措施，其中属于技术措施的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","落实管理人员责任",false,{"key":16,"text":17,"correct":14},"B","优化工作流程",{"key":19,"text":20,"correct":21},"C","改进施工方法",true,{"key":23,"text":24,"correct":14},"D","强化奖惩机制","技术措施。分析由于技术(包括设计和施工的技术)的原因而影响项目目标实现的问题，并采取相应的措施，如调整设计、改进施工方法和改变施工机具等。AB是组织措施，D是管理措施。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]