[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117063":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117063,789,1,"单选题","分析和论证施工成本目标实现的可能性，并对施工成本目标的分解通过（）进行的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制施工成本规划",true,{"key":16,"text":17,"correct":18},"B","编制施工成本比较报表",false,{"key":20,"text":21,"correct":18},"C","编制工作任务分工表",{"key":23,"text":24,"correct":18},"D","编制施工组织设计","施工成本目标的分解指的是通过编制施工成本规划，分析和论证施工成本目标实现的可能性，并对施工成本目标进行分解。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]