[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117061":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117061,789,1,"单选题","建设工程项目目标动态控制的核心是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合理确定计划值",false,{"key":16,"text":17,"correct":14},"B","认真收集实际值",{"key":19,"text":20,"correct":14},"C","适当调整工程项目目标",{"key":22,"text":23,"correct":24},"D","比较分析,采取纠偏措施",true,"项目目标动态控制的核心，在项目实施过程中定期进行项目目标计划值和实际值比较，发现项目目标偏离时采取纠偏措施。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]