[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117057":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117057,789,1,"单选题","需要编制单位工程施工组织设计的工程项目是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","新建居民小区工程",false,{"key":16,"text":17,"correct":18},"B","发电厂干灰库烟囱工程",true,{"key":20,"text":21,"correct":14},"C","工厂整体搬迁工程",{"key":23,"text":24,"correct":14},"D","拆除工程定向爆破工程","单位工程施工组织设计是以单位工程(如一栋楼房、一个烟囱、一段道路、一座桥等)为对象编制的，在施工组织总设计的指导下，由直接组织施工的单位根据施工图设计进行编制，用以直接指导单位工程的施工活动，是施工单位编制分部(分项)工程施工组织设计和季、月、旬施工计划的依据。黑钻押题，请用金考典考试软件 ,考前免费更新 www.jinkaodian.com",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]