[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117051":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117051,789,1,"单选题","对整个建设工程项目的施工进行战略部署，并且是指导全局性施工的技术和经济纲要的文件是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工总平面图",false,{"key":16,"text":17,"correct":18},"B","施工组织总设计",true,{"key":20,"text":21,"correct":14},"C","施工部署及施工方案",{"key":23,"text":24,"correct":14},"D","施工图设计文件","施工部署和施工方案主要内容是全面部署施工任务，合理安排施工顺序，确定主要工程的施工方案;施工平面布置主要是施工方案及进度计划在空间上的全面安排。只有施工组织总设计是对整个工程施工的战部署和指导全局性施工的技术、经济纲要文件。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]