[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117044":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117044,789,1,"单选题","某项目部根据项目特点制定了投资控制、进度控制、合同管理、付款和设计变更等工作流程，这些工作流程组织属于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","物质流程组织",false,{"key":16,"text":17,"correct":18},"B","管理工作流程组织",true,{"key":20,"text":21,"correct":14},"C","信息处理工作流程组织",{"key":23,"text":24,"correct":14},"D","施工工作流程组织","工作流程组织包括： （1）管理工作流程组织（如投资控制、进度控制、合同管理、付款和设计变更流程）； （2）信息处理工作流程组织，如与生成月度进度报告有关的数据处理流程； （3）物质流程组织，如钢结构深化设计工作流程，弱电工程物资采购工作流程，外立面施工工作流程等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]