[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117041":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117041,789,1,"单选题","编制施工管理任务分工表，涉及到的事项有：①确定工作部门或个人的工作任务；②项目管理任务分解；③编制任务分工表。正确的编制程序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①②③",false,{"key":16,"text":17,"correct":18},"B","②①③",true,{"key":20,"text":21,"correct":14},"C","③②①",{"key":23,"text":24,"correct":14},"D","②③①","为了编制项目管理任务分工表，首先应对项目实施的各阶段的费用(投资或成本)控制、进度控制、质量控制、合同管理、信息管理和组织与协调等管理任务进行详细分解，在项目管理任务分解的基础上定义项目经理和费用(投资或成本)控制、进度控制、质量控制、合同管理、信息管理和组织与协调等主管工作部门或主管人员的工作任务。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]