[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117039":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117039,789,1,"单选题","施工项目管理机构编制项目管理任务分工表之前要完成的工作是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","明确各项管理工作的工作流程",false,{"key":16,"text":17,"correct":14},"B","落实各工作部门的具体人员",{"key":19,"text":20,"correct":21},"C","对项目管理任务进行详细分解",true,{"key":23,"text":24,"correct":14},"D","对各项管理工作的执行情况进行检查","施工单位编制项目管理任务分工表前，应结合项目的特点，对项目实施各阶段的费用（投资或成本）控制、进度控制、质量控制、合同管理、信息管理和组织与协调等管理任务进行详细分解。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]