[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117036":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117036,789,1,"单选题","对项目的结构进行逐层分解，反映项目所有工作任务的组织工具是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目结构图",true,{"key":16,"text":17,"correct":18},"B","组织结构",false,{"key":20,"text":21,"correct":18},"C","合同结构图",{"key":23,"text":24,"correct":18},"D","工作流程图","项目结构图是一个组织工具，通过树状图的方式对一个项目的结构进行逐层分解，以反映组成该项目的所有工作任务。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]