[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117034":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117034,789,1,"单选题","建设过程施工方进度目标能否实现的决定性因素是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目经理",false,{"key":16,"text":17,"correct":18},"B","组织体系",true,{"key":20,"text":21,"correct":14},"C","施工方案",{"key":23,"text":24,"correct":14},"D","信息技术","组织是目标能否实现的决定性因素，为实现项目的进度目标，应充分重视健全项目管理的组织体系。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]