[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117020":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117020,789,1,"单选题","建设工程项目的全寿命周期包括项目的（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","可行性研究阶段、设计阶段、施工阶段",false,{"key":16,"text":17,"correct":14},"B","可行性研究阶段、施工阶段、使用阶段",{"key":19,"text":20,"correct":14},"C","决策阶段、实施阶段、保修阶段",{"key":22,"text":23,"correct":24},"D","决策阶段、实施阶段、使用阶段",true,"建设工程项目的全寿命周期包括项目的决策阶段、实施阶段和使用阶段。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]