[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117017":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117017,789,1,"单选题","某工作项目施工采用施工总承包模式，其中电气设备由业主指定的分包单位采购和安装，则在施工中分包单位必须接受（ ）工作指令，服从其总体项目管理。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","业主",false,{"key":16,"text":17,"correct":14},"B","设计方",{"key":19,"text":20,"correct":21},"C","施工总承包方",true,{"key":23,"text":24,"correct":14},"D","项目监理方","施工总承包方对所承包的建设工程承担施工任务的执行和组织的总的责任，分包施工方承担合同所规定的分包施工任务，以及相应的项目管理任务。若采用施工总承包或施工总承包管理模式，分包方(不论是一般的分包方，或由业主指定的分包方)必须热爱施工总承包方或施工总承包管理方的工作指令，服从其总体的项目管理。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]