[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-788-8":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":603},{"id":5,"name":6,"category":7,"favorite":8},788,"二建建设工程法规及相关知识","建筑工程",0,8,50,2902,[13,34,46,58,70,82,94,106,118,130,142,154,166,178,189,198,210,221,233,245,257,269,281,293,305,317,329,341,353,363,374,383,395,407,419,429,441,453,462,473,483,495,507,519,531,543,555,567,579,591],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":20,"analysis":33},1114434,1,"单选题","关于施工许可证，下列表述正确的是()。",[19,23,27,30],{"key":20,"text":21,"correct":22},"A","颁发施工许可证只是表明主管部门对开工条件的认可",true,{"key":24,"text":25,"correct":26},"B","只要颁发了施工许可证就不会再被废止",false,{"key":28,"text":29,"correct":26},"C","颁发了施工许可证后，工程施工发生中止超一年的，应该重新申请施工许可证",{"key":31,"text":32,"correct":26},"D","领取了施工许可证后，无论什么情况都必须开工建设","",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":31,"analysis":33},1114435,"下列选项中，符合《建筑法》有关施工许可证规定的说法或做法的是（）。",[38,40,42,44],{"key":20,"text":39,"correct":26},"为争取早日竣工，建设单位可先行开工建设，但最迟应该在开工后1个月内申请补办施工许可证",{"key":24,"text":41,"correct":26},"开工前，建设单位可申请延期办理施工许可证，延期至多允许3个月",{"key":28,"text":43,"correct":26},"取得施工许可证后，工程未按期开工的，该施工许可证将在3个月后自行废止",{"key":31,"text":45,"correct":22},"取得施工许可证后，工程因故中止，建设单位在一个月内向发证机关递交了报告",{"id":47,"libraryId":5,"type":15,"typeLabel":16,"stem":48,"options":49,"answer":20,"analysis":33},1114436,"建设工程因故中止施工一年者，恢复施工时，该建设单位应当（）。",[50,52,54,56],{"key":20,"text":51,"correct":22},"报发证机关核验施工许可证",{"key":24,"text":53,"correct":26},"重新领取施工许可证",{"key":28,"text":55,"correct":26},"向发证机关报告",{"key":31,"text":57,"correct":26},"向发证机关备案",{"id":59,"libraryId":5,"type":15,"typeLabel":16,"stem":60,"options":61,"answer":28,"analysis":33},1114437,"某建设单位欲新建一座大型综合市场，于2012年3月20日领到工程施工许可证。开工后因故于2012年10月15日中止施工。根据建筑法施工许可证制度的规定，该建设单位向施工许可证发证机关报告的最迟期限应是2012年（）。",[62,64,66,68],{"key":20,"text":63,"correct":26},"10月15日",{"key":24,"text":65,"correct":26},"10月22日",{"key":28,"text":67,"correct":22},"11月14日",{"key":31,"text":69,"correct":26},"12月14日",{"id":71,"libraryId":5,"type":15,"typeLabel":16,"stem":72,"options":73,"answer":31,"analysis":33},1114438,"在城市规划区的建筑工程，建设单位在依法办理用地批准手续前，必须先取得该工程（）。",[74,76,78,80],{"key":20,"text":75,"correct":26},"施工许可证",{"key":24,"text":77,"correct":26},"建设工程规划许可证",{"key":28,"text":79,"correct":26},"开工报告",{"key":31,"text":81,"correct":22},"建设用地规划许可证",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":24,"analysis":33},1114439,"批准开工报告的建筑工程，因故不能按期开工超过（）的，应当重新办理开工报告的批准手续。",[86,88,90,92],{"key":20,"text":87,"correct":26},"3个月",{"key":24,"text":89,"correct":22},"6个月",{"key":28,"text":91,"correct":26},"1年",{"key":31,"text":93,"correct":26},"2年",{"id":95,"libraryId":5,"type":15,"typeLabel":16,"stem":96,"options":97,"answer":31,"analysis":33},1114440,"根据我国《建筑法》的规定，（）建筑工程在施工前必须办理施工许可证。",[98,100,102,104],{"key":20,"text":99,"correct":26},"投资200万元的古建筑修缮",{"key":24,"text":101,"correct":26},"造价为600万元的抢险救灾",{"key":28,"text":103,"correct":26},"总投资5000万元的军用房屋",{"key":31,"text":105,"correct":22},"建筑面积为8000m2的市政广场建设",{"id":107,"libraryId":5,"type":15,"typeLabel":16,"stem":108,"options":109,"answer":24,"analysis":33},1114441,"根据我国《建设工程安全生产管理条例》规定，建设单位在申请领取施工许可证时，应当提供（）。",[110,112,114,116],{"key":20,"text":111,"correct":26},"建设工程进度及投资计划",{"key":24,"text":113,"correct":22},"建设工程有关安全施工措施的资料",{"key":28,"text":115,"correct":26},"建设工程有关质量保证措施的资料",{"key":31,"text":117,"correct":26},"建设工程安全生产人员的有关资料",{"id":119,"libraryId":5,"type":15,"typeLabel":16,"stem":120,"options":121,"answer":31,"analysis":33},1114442,"某建设单位于2014年3月1日领取了施工许可征，由于某种原因工程未能按期开工，该建设单位按照《建筑法》的规定向发证机关多次办理了申请延期手续，该工程最迟应当在()开工。",[122,124,126,128],{"key":20,"text":123,"correct":26},"2014年5月1日",{"key":24,"text":125,"correct":26},"2014年6月1日",{"key":28,"text":127,"correct":26},"2014年9月1日",{"key":31,"text":129,"correct":22},"2014年12月1日",{"id":131,"libraryId":5,"type":15,"typeLabel":16,"stem":132,"options":133,"answer":28,"analysis":33},1114443,"《建筑工程施工许可管理办法》规定，对于采用虚假证明文件骗取施工许可证的，由()，并对责任单位处以罚款；构成犯罪的，依法追究刑事责任。",[134,136,138,140],{"key":20,"text":135,"correct":26},"工商行政管理部门收回施工许可证，责令停止施工",{"key":24,"text":137,"correct":26},"工商行政管理部门收回施工许可证，吊销资质证书",{"key":28,"text":139,"correct":22},"原发证机关收回施工许可证，责令停止施工",{"key":31,"text":141,"correct":26},"原发证机关收回施工许可证，吊销资质证书",{"id":143,"libraryId":5,"type":15,"typeLabel":16,"stem":144,"options":145,"answer":20,"analysis":33},1114444,"建设单位在取得建设用地规划许可证后，方可向县级以上地方人民政府土地主管部门申请用地，经()审批后，由土地主管部门划拨土地。",[146,148,150,152],{"key":20,"text":147,"correct":22},"县级以上人民政府",{"key":24,"text":149,"correct":26},"设区的市级以上人民政府",{"key":28,"text":151,"correct":26},"省级人民政府",{"key":31,"text":153,"correct":26},"国务院",{"id":155,"libraryId":5,"type":15,"typeLabel":16,"stem":156,"options":157,"answer":20,"analysis":33},1114445,"某建设单位领取了施工许可证，因故不能在3个月内开工，但又未申请延期。该施工许可证()。",[158,160,162,164],{"key":20,"text":159,"correct":22},"自行废止",{"key":24,"text":161,"correct":26},"重新核验",{"key":28,"text":163,"correct":26},"继续有效",{"key":31,"text":165,"correct":26},"自动延期",{"id":167,"libraryId":5,"type":15,"typeLabel":16,"stem":168,"options":169,"answer":28,"analysis":33},1114446,"对于未取得施工许可证或者为规避办理施工许可证将工程项目分解后擅自施工的，由有管辖权的发证机关责令停止施工，限期改正，对建设单位和施工单位分别处以罚款，对施工单位的罚款额度为()。",[170,172,174,176],{"key":20,"text":171,"correct":26},"5万元以下",{"key":24,"text":173,"correct":26},"4万元以下",{"key":28,"text":175,"correct":22},"3万元以下",{"key":31,"text":177,"correct":26},"2万元以下",{"id":179,"libraryId":5,"type":15,"typeLabel":16,"stem":180,"options":181,"answer":28,"analysis":33},1114447,"对于实行开工报告制度的建设工程，因故不能按期开工超过6个月的，应当()。",[182,184,185,187],{"key":20,"text":183,"correct":26},"申请延期开工",{"key":24,"text":161,"correct":26},{"key":28,"text":186,"correct":22},"重新办理批准手续",{"key":31,"text":188,"correct":26},"备案",{"id":190,"libraryId":5,"type":15,"typeLabel":16,"stem":191,"options":192,"answer":31,"analysis":33},1114448,"在城市规划区内进行建设需要申请用地的,建设单位在依法办理用地批准手续前,必须先取得()。",[193,194,195,197],{"key":20,"text":75,"correct":26},{"key":24,"text":77,"correct":26},{"key":28,"text":196,"correct":26},"拆迁许可证",{"key":31,"text":81,"correct":22},{"id":199,"libraryId":5,"type":15,"typeLabel":16,"stem":200,"options":201,"answer":31,"analysis":33},1114449,"建设单位申请施工许可证时,向办证机关提供的施工图纸及技术资料应当满足()。",[202,204,206,208],{"key":20,"text":203,"correct":26},"施工需要并通过监理单位审査",{"key":24,"text":205,"correct":26},"编制招标文件的要求",{"key":28,"text":207,"correct":26},"工程竣工验收备案的要求",{"key":31,"text":209,"correct":22},"施工需要并按规定通过了审査",{"id":211,"libraryId":5,"type":15,"typeLabel":16,"stem":212,"options":213,"answer":28,"analysis":33},1114450,"建设工程施工许可证应当向工程所在地的（）建设行政主管部门申请领取。",[214,216,218,219],{"key":20,"text":215,"correct":26},"乡政府",{"key":24,"text":217,"correct":26},"镇政府",{"key":28,"text":147,"correct":22},{"key":31,"text":220,"correct":26},"有国务院授权的各级政府",{"id":222,"libraryId":5,"type":15,"typeLabel":16,"stem":223,"options":224,"answer":24,"analysis":33},1114451,"按照《建筑法》的规定，建设工程未办理施工许可证或开工报告审批手续即开始施工，主管部门适当的处理为（）。",[225,227,229,231],{"key":20,"text":226,"correct":26},"责令停止施工",{"key":24,"text":228,"correct":22},"责令其改正，对不符合开工条件的责令停止施工,可以处以罚款",{"key":28,"text":230,"correct":26},"责令停止施工，处合同价款2%以上的罚款",{"key":31,"text":232,"correct":26},"责令限期改正，没收非法所得",{"id":234,"libraryId":5,"type":15,"typeLabel":16,"stem":235,"options":236,"answer":28,"analysis":33},1114452,"某工程按国务院规定于2008年6月1日办理了开工报告审批手续，由于周边关系协调问题一直没有开工，同年12月7日准备开工时，建设单位应当（）。",[237,239,241,243],{"key":20,"text":238,"correct":26},"向批准机关申请延期",{"key":24,"text":240,"correct":26},"报批准机关核验开工报告",{"key":28,"text":242,"correct":22},"重新办理开工报告审批手续",{"key":31,"text":244,"correct":26},"改办施工许可证",{"id":246,"libraryId":5,"type":15,"typeLabel":16,"stem":247,"options":248,"answer":24,"analysis":33},1114453,"下列选项中，违反施工许可证制度的是（）。",[249,251,253,255],{"key":20,"text":250,"correct":26},"农民张某自建一栋500平方米的3层住宅，未办理施工许可证就施工",{"key":24,"text":252,"correct":22},"某工程因地震中止施工，半年后向发证机关作了报告",{"key":28,"text":254,"correct":26},"某工程因供水中止施工，一个月内向发证机关作了报告，半年后恢复施工时还向发证机关作了报告",{"key":31,"text":256,"correct":26},"某工程因宏观调控停建，一个月内向发证机关作了报告，一年后恢复施工时报发证机关核验施工许可证",{"id":258,"libraryId":5,"type":15,"typeLabel":16,"stem":259,"options":260,"answer":24,"analysis":33},1114454,"实行开工报告审批制度的建设工程，对开工报告审查的内容中与颁发施工许可证的工程不同的是（）。",[261,263,265,267],{"key":20,"text":262,"correct":26},"资金到位情况",{"key":24,"text":264,"correct":22},"投资项目市场预测情况",{"key":28,"text":266,"correct":26},"设计图纸是否满足施工要求",{"key":31,"text":268,"correct":26},"现场条件是否三通一平等",{"id":270,"libraryId":5,"type":15,"typeLabel":16,"stem":271,"options":272,"answer":24,"analysis":33},1114455,"建设工程开工后因故中止施工，建设单位应当自中止施工之日起的（）内向施工许可证发证机关报告。",[273,275,277,279],{"key":20,"text":274,"correct":26},"15日",{"key":24,"text":276,"correct":22},"30日",{"key":28,"text":278,"correct":26},"60日",{"key":31,"text":280,"correct":26},"90日",{"id":282,"libraryId":5,"type":15,"typeLabel":16,"stem":283,"options":284,"answer":20,"analysis":33},1114456,"在施工许可证的法定审批条件中，关于建设用地的说法正确的是（）。",[285,287,289,291],{"key":20,"text":286,"correct":22},"任何单位或个人进行建设需要使用土地的，必须依法申请使用国有土地",{"key":24,"text":288,"correct":26},"在城市规划区以划拨方式提供国有土地使用权的建设工程，可直接办理建设工程规划许可证",{"key":28,"text":290,"correct":26},"在城市规划区以出让方式取得建设用地使用权的建设工程，签订国有土地使用权出让合同后，还要补办建设用地规划许可证",{"key":31,"text":292,"correct":26},"乡村公益事业建设工程，须核发建设用地规划许可证",{"id":294,"libraryId":5,"type":15,"typeLabel":16,"stem":295,"options":296,"answer":24,"analysis":33},1114457,"规避办理施工许可证应承担的法律责任是（）。",[297,299,301,303],{"key":20,"text":298,"correct":26},"责令停止施工，对建设单位处以罚款",{"key":24,"text":300,"correct":22},"责令停止施工，对建设单位和施工单位分别处以罚款",{"key":28,"text":302,"correct":26},"对不符合开工条件的，责令停止施工，处合同价1%以上2%以下的罚款",{"key":31,"text":304,"correct":26},"对责任者追究刑事责任",{"id":306,"libraryId":5,"type":15,"typeLabel":16,"stem":307,"options":308,"answer":31,"analysis":33},1114458,"关于禁止投标人以行贿的手段谋取中标，按《反不正当竞争法》规定，没有违法的行为是（ ）",[309,311,313,315],{"key":20,"text":310,"correct":26},"经营者采用现金贿赂交易相对方的工作人员，但接受贿赂的人员如实入帐了",{"key":24,"text":312,"correct":26},"经营者采用财物或者其他手段贿赂受交易相对方委托办理相关事务的单位或者个人",{"key":28,"text":314,"correct":26},"经营者采用财务或者其他手段贿赂利用职权或者影响力影响交易的单位或者个人",{"key":31,"text":316,"correct":22},"经营者公开向交易相对方支付折扣，或者向中间人支付佣金",{"id":318,"libraryId":5,"type":15,"typeLabel":16,"stem":319,"options":320,"answer":20,"analysis":33},1114459,"建设工程领取施工许可证后因故不能正常开工可申请延期，但延期以两次为限，每次不超过（）个月。",[321,323,325,327],{"key":20,"text":322,"correct":22},"3",{"key":24,"text":324,"correct":26},"4",{"key":28,"text":326,"correct":26},"5",{"key":31,"text":328,"correct":26},"6",{"id":330,"libraryId":5,"type":15,"typeLabel":16,"stem":331,"options":332,"answer":28,"analysis":33},1114460,"根据我国《建筑法》的规定，以下工程项目在开工前依法需要申请施工许可证的是()。",[333,335,337,339],{"key":20,"text":334,"correct":26},"建筑面积在200㎡以下的建筑工程",{"key":24,"text":336,"correct":26},"投资额为20万元的建筑工程",{"key":28,"text":338,"correct":22},"华裔商人的个人投资50万元的工程",{"key":31,"text":340,"correct":26},"抢险救灾工程",{"id":342,"libraryId":5,"type":15,"typeLabel":16,"stem":343,"options":344,"answer":31,"analysis":33},1114461,"某建设单位2010年9月1日领取了施工许可证，由于特殊原因不能按期开工，故向发证机关申请延期。根据我国《建筑法》的规定，下列关于延期的说法中，正确的是()。",[345,347,349,351],{"key":20,"text":346,"correct":26},"领取施工许可证不能延期",{"key":24,"text":348,"correct":26},"可以延期但只能延期一次",{"key":28,"text":350,"correct":26},"延期以两次为限，每次不超过2个月",{"key":31,"text":352,"correct":22},"超过延期时限的，施工许可证自行废止",{"id":354,"libraryId":5,"type":15,"typeLabel":16,"stem":355,"options":356,"answer":31,"analysis":33},1114462,"由城市、人民政府城乡规划主管部门依据控制性详细规划核定建设用地的位置、面积、允许建设的范围，核发（）。",[357,359,361,362],{"key":20,"text":358,"correct":26},"施工许可制度",{"key":24,"text":360,"correct":26},"安全生产许可证",{"key":28,"text":77,"correct":26},{"key":31,"text":81,"correct":22},{"id":364,"libraryId":5,"type":15,"typeLabel":16,"stem":365,"options":366,"answer":31,"analysis":33},1114463,"甲建设单位2011年9月1日领取了施工许可证。由于特殊原因不能按期开工，故向发证机关申请延期。根据我国《建筑法》的规定，则关于延期的说法正确的是（）。",[367,369,371,373],{"key":20,"text":368,"correct":26},"可以延期，但只能延期一次",{"key":24,"text":370,"correct":26},"领取施工许可证延期次数不受限制",{"key":28,"text":372,"correct":26},"延期以两次为限，每次不超过两个月",{"key":31,"text":352,"correct":22},{"id":375,"libraryId":5,"type":15,"typeLabel":16,"stem":376,"options":377,"answer":28,"analysis":33},1114464,"建筑施工企业确定后，在建筑工程开工前，建设单位应当按照国家规定向工程所在地县级以上人民政府建设行政主管部门申请领取（）。",[378,380,381,382],{"key":20,"text":379,"correct":26},"建设用地规划证可证",{"key":24,"text":77,"correct":26},{"key":28,"text":75,"correct":22},{"key":31,"text":360,"correct":26},{"id":384,"libraryId":5,"type":15,"typeLabel":16,"stem":385,"options":386,"answer":24,"analysis":33},1114465,"某房地产开发公司拟在某市旧城区一块地上开发住宅小区工程项目，建设工程合同价格为20000万元，工期为18个月，按照国家有关规定，该开发公司应当向工程所在地的区政府建设局申请领取施工许可证。申请领取施工许可证的时间最迟应当在（）。",[387,389,391,393],{"key":20,"text":388,"correct":26},"确定施工单位前",{"key":24,"text":390,"correct":22},"住宅小区工程开工前",{"key":28,"text":392,"correct":26},"确定监理单位前",{"key":31,"text":394,"correct":26},"住宅小区工程竣工验收前",{"id":396,"libraryId":5,"type":15,"typeLabel":16,"stem":397,"options":398,"answer":24,"analysis":33},1114466,"根据《消防法》关于建设工程消防设计文件的审核与备案的规定，下列说法正确的是（）。",[399,401,403,405],{"key":20,"text":400,"correct":26},"特殊建设工程以外的其他建设工程，建设单位未提供满足施工图纸需要的消防设计图纸及技术资料的，有关部门可以发放施工许可证",{"key":24,"text":402,"correct":22},"特殊建设工程经消防设计审查不合格的，建设单位、施工单位不得施工",{"key":28,"text":404,"correct":26},"特殊建设工程未经消防设计审查，建设单位、施工单位可以施工",{"key":31,"text":406,"correct":26},"特殊建设工程以外的其他建设工程，建设单位未提供满足施工图纸需要的消防设计图纸及技术资料的，有关部门可以批准开工报告",{"id":408,"libraryId":5,"type":15,"typeLabel":16,"stem":409,"options":410,"answer":24,"analysis":33},1114467,"建设工程施工许可证的申请主体是该工程的（）。",[411,413,415,417],{"key":20,"text":412,"correct":26},"施工单位",{"key":24,"text":414,"correct":22},"建设单位",{"key":28,"text":416,"correct":26},"监理单位",{"key":31,"text":418,"correct":26},"咨询服务单位",{"id":420,"libraryId":5,"type":15,"typeLabel":16,"stem":421,"options":422,"answer":28,"analysis":33},1114468,"某建设工程按规定于2012年6月1日办理了开工报告审批手续，但因故一直没有开工，同年12月7日准备开工时，建设单位应当（）。",[423,425,426,428],{"key":20,"text":424,"correct":26},"向发证机关申请延期",{"key":24,"text":240,"correct":26},{"key":28,"text":427,"correct":22},"重新办理开工报告批准手续",{"key":31,"text":244,"correct":26},{"id":430,"libraryId":5,"type":15,"typeLabel":16,"stem":431,"options":432,"answer":24,"analysis":33},1114469,"在城市规划区的建筑工程，已经取得规划许可证是领取施工许可证的条件之一，下列对规划许可证领取的理解正确的是（）。",[433,435,437,439],{"key":20,"text":434,"correct":26},"以划拨方式提供国国有土地使用权的建设项目，建设单位应当先申请土地使用权",{"key":24,"text":436,"correct":22},"以划拨方式提供国国有土地使用权的建设项目，建设单位应当先取得规划许可证后申请用地",{"key":28,"text":438,"correct":26},"以出让方式取得国有土地使用权的建设项目，在取得规划许可证后，方可签订国有土地使用权出让合同",{"key":31,"text":440,"correct":26},"不管何种方式取得的土地，都必须在取得土地使用权后，办理规划许可证",{"id":442,"libraryId":5,"type":15,"typeLabel":16,"stem":443,"options":444,"answer":20,"analysis":33},1114470,"某建筑工程因故中止施工3个月，建设单位需要做的工作有（）。",[445,447,449,451],{"key":20,"text":446,"correct":22},"应当自中止施工之日起一个月内，向发证机关报告",{"key":24,"text":448,"correct":26},"应当自中止施工之日起三个月内，申请延期",{"key":28,"text":450,"correct":26},"应当自中止施工之日起一个月内，报发证机关核验施工许可证",{"key":31,"text":452,"correct":26},"应当自中止施工之日起三个月内，重新办理施工许可证",{"id":454,"libraryId":5,"type":15,"typeLabel":16,"stem":455,"options":456,"answer":28,"analysis":33},1114471,"建设单位应当报发证机关核验施工许可证的前提是，中止施工满（）的工程恢复施工。",[457,459,460,461],{"key":20,"text":458,"correct":26},"1个月",{"key":24,"text":87,"correct":26},{"key":28,"text":91,"correct":22},{"key":31,"text":93,"correct":26},{"id":463,"libraryId":5,"type":15,"typeLabel":16,"stem":464,"options":465,"answer":24,"analysis":33},1114472,"对采用虚假证明文件骗取施工许可证尚未构成犯罪的，应由发证机关（）。",[466,467,469,471],{"key":20,"text":300,"correct":26},{"key":24,"text":468,"correct":22},"撤销施工许可证，责令停止施工并处1万元以上3万元以下罚款",{"key":28,"text":470,"correct":26},"宣布该施工许可证无效，责令停止施工，没收非法所得",{"key":31,"text":472,"correct":26},"责令停止施工，没收违法所得的，处以5000元以上30000元以下的罚款",{"id":474,"libraryId":5,"type":15,"typeLabel":16,"stem":475,"options":476,"answer":31,"analysis":33},1114473,"按规定批准开工报告不再办理施工许可证的建设工程，必须符合（）的规定。",[477,479,480,482],{"key":20,"text":478,"correct":26},"施工许可证发证机关",{"key":24,"text":147,"correct":26},{"key":28,"text":481,"correct":26},"省市人民政府",{"key":31,"text":153,"correct":22},{"id":484,"libraryId":5,"type":15,"typeLabel":16,"stem":485,"options":486,"answer":31,"analysis":33},1114474,"某房地产开发公司在某市老城区拟开发的一住宅小区项目涉及到拆迁，则房地产公司申领施工许可证前，()。",[487,489,491,493],{"key":20,"text":488,"correct":26},"拆迁工作必须全部完成",{"key":24,"text":490,"correct":26},"拆迁补偿安置资金全部到位",{"key":28,"text":492,"correct":26},"拆迁工程量已完成50％",{"key":31,"text":494,"correct":22},"有保证工程质量和安全的具体措施",{"id":496,"libraryId":5,"type":15,"typeLabel":16,"stem":497,"options":498,"answer":28,"analysis":33},1114475,"因项目开发，某房地产公司必须在申领施工许可证前，先办妥建设用地管理和城市规划管理方面的手续，在此阶段最后取得的是该项目的（）。",[499,501,503,505],{"key":20,"text":500,"correct":26},"用地规划许可证",{"key":24,"text":502,"correct":26},"国有土地使用权批准文件",{"key":28,"text":504,"correct":22},"工程规划许可证",{"key":31,"text":506,"correct":26},"土地使用权证",{"id":508,"libraryId":5,"type":15,"typeLabel":16,"stem":509,"options":510,"answer":20,"analysis":33},1114476,"甲公司新建某商业项目的建设工期为24个月。根据《建筑工程施工许可管理办法》，甲公司下列条件符合领取施工许可证必备条件的是()。",[511,513,515,517],{"key":20,"text":512,"correct":22},"已经取得建设工程规划许可证",{"key":24,"text":514,"correct":26},"拆迁进度已经超过50%",{"key":28,"text":516,"correct":26},"施工图纸已由设计院完成",{"key":31,"text":518,"correct":26},"建设资金已达到合同价的25%",{"id":520,"libraryId":5,"type":15,"typeLabel":16,"stem":521,"options":522,"answer":31,"analysis":33},1114477,"由于某项目建设涉及拆迁，按照《建筑工程施工许可管理办法》的规定，在申领施工许可证前,拆迁工作（）。",[523,525,527,529],{"key":20,"text":524,"correct":26},"必须全部完成",{"key":24,"text":526,"correct":26},"所需求的补偿安置资金全部到位",{"key":28,"text":528,"correct":26},"应完成50%以上",{"key":31,"text":530,"correct":22},"进度已满足施工的要求",{"id":532,"libraryId":5,"type":15,"typeLabel":16,"stem":533,"options":534,"answer":20,"analysis":33},1114478,"根据《建筑法》规定，申请领取建筑工程施工许可证的条件不包括（）。",[535,537,539,541],{"key":20,"text":536,"correct":22},"已经确定监理单位",{"key":24,"text":538,"correct":26},"已经确定建筑施工企业",{"key":28,"text":540,"correct":26},"建设资金已经落实",{"key":31,"text":542,"correct":26},"施工图设计文件已经按照规定进行了审查",{"id":544,"libraryId":5,"type":15,"typeLabel":16,"stem":545,"options":546,"answer":28,"analysis":33},1114479,"按照《建筑法》的规定，下列关于建设单位申请领取施工许可证应具备的法定条件的表述中，正确的是（）。",[547,549,551,553],{"key":20,"text":548,"correct":26},"需要拆迁的，已取得房屋拆迁许可证",{"key":24,"text":550,"correct":26},"需要使用建设用地的，已经办理了用地规划许可证",{"key":28,"text":552,"correct":22},"有满足施工需要的技术资料和按规定审查合格的施工图设计文件",{"key":31,"text":554,"correct":26},"建设投资全部到位",{"id":556,"libraryId":5,"type":15,"typeLabel":16,"stem":557,"options":558,"answer":28,"analysis":33},1114480,"建设单位为工程项目办理质量监督手续应在()。",[559,561,563,565],{"key":20,"text":560,"correct":26},"领取工程规划许可证前",{"key":24,"text":562,"correct":26},"领取工程规划许可证时",{"key":28,"text":564,"correct":22},"领取施工许可证前",{"key":31,"text":566,"correct":26},"领取施工许可证后",{"id":568,"libraryId":5,"type":15,"typeLabel":16,"stem":569,"options":570,"answer":31,"analysis":33},1114481,"《建筑工程施工许可管理办法》规定，在中华人民共和国境内从事各类房屋建筑及其附属设施的建造、装修装饰和与其配套的线路、管道、设备的安装，以及城镇市政基础设施工程的施工，建设单位在开工前应当依照本办法的规定，向()申请领取施工许可证。",[571,573,575,577],{"key":20,"text":572,"correct":26},"施工单位所在地的县级以上人民政府工商行政管理部门",{"key":24,"text":574,"correct":26},"施工单位所在地的县级以上人民政府建设行政主管部门",{"key":28,"text":576,"correct":26},"工程所在地的县级以上人民政府工商行政管理部门",{"key":31,"text":578,"correct":22},"工程所在地的县级以上人民政府建设行政主管部门",{"id":580,"libraryId":5,"type":15,"typeLabel":16,"stem":581,"options":582,"answer":20,"analysis":33},1114482,"需要进行消防设计的建筑工程，建设单位应当将建筑工程的消防设计图纸及有关资料报送（）审核。",[583,585,587,589],{"key":20,"text":584,"correct":22},"公安消防部门",{"key":24,"text":586,"correct":26},"建设工程安全监督机构",{"key":28,"text":588,"correct":26},"建设行政主管部门",{"key":31,"text":590,"correct":26},"上级主管部门",{"id":592,"libraryId":5,"type":15,"typeLabel":16,"stem":593,"options":594,"answer":20,"analysis":33},1114483,"经批准需要使用国有建设用地的建设项目，申请建设用地须经（）批准。",[595,597,599,601],{"key":20,"text":596,"correct":22},"县级以上土地行政主管部门",{"key":24,"text":598,"correct":26},"当地人民政府",{"key":28,"text":600,"correct":26},"土地行政主管部门的同级人民政府",{"key":31,"text":602,"correct":26},"土地行政主管部门的上级土地管理部门",[604,607,610,613,616,619],{"id":15,"name":605,"category":7,"favorite":606},"领导干部任职前廉政法规知识测试题",92,{"id":608,"name":609,"category":7,"favorite":15},595,"建筑结构与设备",{"id":611,"name":612,"category":7,"favorite":15},715,"招标采购专业知识与法律法规",{"id":614,"name":615,"category":7,"favorite":15},848,"市政方向-通用基础",{"id":617,"name":618,"category":7,"favorite":8},534,"BIM工程师",{"id":620,"name":618,"category":7,"favorite":8},535]