[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117128":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117128,788,1,"单选题","施工合同诉讼当事人对工程款付款时间没有约定或约定不明确，建设工程尚未交付，已提交竣工结算文件，则应付工程款时间为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","竣工验收合格之日",false,{"key":16,"text":17,"correct":14},"B","当事人起诉之日",{"key":19,"text":20,"correct":21},"C","提交竣工结算文件之日",true,{"key":23,"text":24,"correct":14},"D","判决生效之日","下列时间视为应付款时间：(1)建设工程已实际交付的，为交付之日；(2)建设工程没有交付的，为提交竣工结算文件之日；(3)建设工程未交付，工程价款也未结算的，为当事人起诉之日。故C选项正确。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]