[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117126":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117126,788,1,"单选题","建设工程施工合同对付款时间没有约定或约定不明，则应付款时间为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程价款确定之日",false,{"key":16,"text":17,"correct":14},"B","建设工程已竣工验收的，为竣工验收合格之日",{"key":19,"text":20,"correct":21},"C","建设工程未交付，工程款价也未结算的，为当事人起诉之日",true,{"key":23,"text":24,"correct":14},"D","建设工程未交付的，为竣工结算完成之日","下列时间视为应付款时间：（1）建设工程已实际交付的，为交付之日；（2）建设工程没有交付的，为提交竣工结算文件之日；（3）建设工程未交付，工程价款也未结算的，为当事人起诉之日。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]