[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117120":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117120,788,1,"单选题","关于建设工程施工合同变更的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同变更内容约定不明确，推定为未变更",true,{"key":16,"text":17,"correct":18},"B","合同变更与工程变更的范围一致",false,{"key":20,"text":21,"correct":18},"C","合同变更协议自签字之日起生效",{"key":23,"text":24,"correct":18},"D","发包人可依据其单方意思变更合同","当事人协商一致，可以变更合同。法律、行政法规规定变更合同应当办理批准、登记等手续的，依照其规定。当事人对合同变更的内容约定不明确的，推定为未变更。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]