[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1116978":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1116978,788,1,"单选题","某建筑公司向供货商采购某种国家定价的特种材料，合同签订时价格为4000元／吨，约定6月1日运至某工地。后供货商迟迟不予交货，8月下旬，国家调整价格为3400元／吨，供货商急忙交货。双方为结算价格产生争议。下列说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","应按合同约定的价格4000元／吨结算",false,{"key":16,"text":17,"correct":18},"B","应按国家确定的最新价格3400元／吨结算",true,{"key":20,"text":21,"correct":14},"C","应当按新旧价格的平均值结算",{"key":23,"text":24,"correct":14},"D","双方协商确定，协商不成的应当解除合同","逾期交付标的物的，遇价格上涨时，按照原价格执行；价格下降时，按照新价格执行。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]