[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1116852":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1116852,788,1,"单选题","根据《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释》，下列情形中，造成建设工程质量缺陷，发包人应当承担过错责任的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","未申领施工许可证",false,{"key":16,"text":17,"correct":14},"B","迟延提供设计文件",{"key":19,"text":20,"correct":21},"C","直接指定分包人分包专业工程",true,{"key":23,"text":24,"correct":14},"D","拖欠工程款","《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释》，下列情形中，造成建设工程质量缺陷，发包人应当承担过错责任：(1)提供的设计有缺陷；(2)提供或指定购买的建筑材料、建筑构配件、设备不符合强制性标准；(3)直接指定分包人分包专业工程。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]