[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1116804":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1116804,788,1,"单选题","在工程建设中，如果拟采用的新技术、新工艺、新材料不符合现行强制性标准规定的应当由（ ）组织专题技术论证，报批准标准的建设行政主管部门或者国务院有关主管部门审定",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","拟采用单位提请建设单位",true,{"key":16,"text":17,"correct":18},"B","施工单位",false,{"key":20,"text":21,"correct":18},"C","监理单位",{"key":23,"text":24,"correct":18},"D","设计单位","《实施工程建设强制性标准监督规定》规定，在工程建设中，如果拟采用的新技术、新工艺、新材料不符合现行强制性标准规定的，应当由拟采用单位提请建设单位组织专题技术论证，报批准标准的建设行政主管部门或者国务院有关主管部门审定。A项正确。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]