[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1116754":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1116754,788,1,"单选题","（2019年） 因设计优化使得施工总承包项目现场暂时停止施工的，增加的现场防护费用由（ ）承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位",true,{"key":16,"text":17,"correct":18},"B","设计单位",false,{"key":20,"text":21,"correct":18},"C","总承包单位",{"key":23,"text":24,"correct":18},"D","分包单位","《建设工程安全生产管理条例》规定，施工现场暂时停止施工的，施工单位应当做好现场防护，所需费用由责任方承担，或者按照合同约定执行。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]