[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1116677":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1116677,788,1,"单选题","根据《绿色施工导则》，在土方作业阶段采取洒水、覆盖等措施后，作业区目测扬尘高度应当小于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2米",false,{"key":16,"text":17,"correct":18},"B","1.5米",true,{"key":20,"text":21,"correct":14},"C","1米",{"key":23,"text":24,"correct":14},"D","0.5米","土方作业阶段，采取洒水、覆盖等措施，达到作业区目测扬尘高度小于1.5m,不扩散到场区外。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]