[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1116620":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1116620,788,1,"单选题","（2017年）关于建设工程竣工验收备案的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工企业自竣工验收合格之日起 15 日内办理备案",false,{"key":16,"text":17,"correct":14},"B","竣工验收备案必须提交监理单位出具的工程正式验收合格证明文件",{"key":19,"text":20,"correct":14},"C","工程竣工验收完成后，建设单位应向备案机关提交工程质量监督报告",{"key":22,"text":23,"correct":24},"D","工程竣工验收备案表一式二份，1 份由建设单位保存，1 份留备案机关存档",true,"A 是建设单位办理；B 不需要监理的证明文件；C 是工程质量监督机构向备案机关提交。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]