[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1116447":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1116447,788,1,"单选题","（2019年） 某建设工程承包人在工程完工后于 2 月 1 日提交了竣工验收报告，发包人未组织验收；3 月 1 日工程 由发包人接收；4 月 1 日承包人提交了结算文件，发包人迟迟未予结算；6 月 1 日，承包人起诉至人民法 院。该工程应付款时间为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3 月 1 日",true,{"key":16,"text":17,"correct":18},"B","2 月 1 日",false,{"key":20,"text":21,"correct":18},"C","4 月 1 日",{"key":23,"text":24,"correct":18},"D","6 月 1 日","当事人对付款时间没有约定或者约定不明的，下列时间视为应付款时间：（1）建设工程已实际 交付的，为交付之日；（2）建设工程没有交付的，为提交竣工结算文件之日；（3）建设工程未交付，工 程价款也未结算的，为当事人起诉之日。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]