[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1116425":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1116425,788,1,"单选题","（2015年） 建设工程未经竣工验收，发包人擅自使用的，该工程竣工日期应为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","提交验收报告之日",false,{"key":16,"text":17,"correct":14},"B","建设工程完工之日",{"key":19,"text":20,"correct":21},"C","转移占有建设工程之日",true,{"key":23,"text":24,"correct":14},"D","竣工验收合格之日","本题考查的是竣工日期。建设工程未经竣工验收，发包人擅自使用的，以转移占有建设工程之日 为竣工日期。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]