[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1116421":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1116421,788,1,"单选题","（2014年） 因设计变更导致建设工程的工程量或者质量标准发生变化，当事人对该部分价款不能协商一致的，可以参照（ ）建设行政主管部门发布的计价方法或者计价标准结算工程价款。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","签约时的签约地",false,{"key":16,"text":17,"correct":14},"B","履约时的签约地",{"key":19,"text":20,"correct":14},"C","履约时的项目所在地",{"key":22,"text":23,"correct":24},"D","签约时的项目所在地",true,"因设计变更导致建设工程的工程量或质量标准发生变化，当事人对该部分工程价款不能协商一致 的，可以参照签订建设工程施工合同时当地建设行政主管部门发布的计价方法或者计价标准结算工程价 款。这个当地指的就是建设工程所在地。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]