[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1116379":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1116379,788,1,"单选题","（2019年） 关于开标的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","开标应当在招标文件确定的提交投标文件截止时间之后公开进行",false,{"key":16,"text":17,"correct":14},"B","开标地点不必为招标文件中预先确定的地点",{"key":19,"text":20,"correct":14},"C","开标由招标人以外的人主持，邀请所有投标人参加",{"key":22,"text":23,"correct":24},"D","开标过程应当记录，并存档备查",true,"A 错误，开标时间应当与招标文件确定的提交投标文件截止时间一致；B 错误，开标地点应当为 招标文件中预先确定的地点；C 错误，开标由招标人主持，邀请所有投标人参加",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]