[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1116235":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1116235,788,1,"单选题","对于暂时不能开工的建设用地，建设单位应该对裸露地面进行覆盖，超过一定时间的，应该进行绿化、铺装或者遮盖。该时间限定为（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","15天",false,{"key":16,"text":17,"correct":14},"B","1个月",{"key":19,"text":20,"correct":21},"C","3个月",true,{"key":23,"text":24,"correct":14},"D","6个月","2020版教材P176 暂时不能开工的建设用地，建设单位应当对裸露地面进行覆盖；超过三个月的，应当进行绿化、铺装或者遮盖。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]