[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1115609":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1115609,788,1,"单选题","甲承建乙发包的工程，在工程实施过程中，乙要求甲完成合同以外的零星项目。对此，甲的不适宜做法是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在接受乙要求的10天内向乙提请施工签证",true,{"key":16,"text":17,"correct":18},"B","提请的签证事项包括了用工数量和单价、机械台班数量和单价、使用材料和金额等",false,{"key":20,"text":21,"correct":18},"C","在乙签证后开始零星项目的施工",{"key":23,"text":24,"correct":18},"D","出于维系良好合作关系的考虑，在乙未签证时开始施工，并自负发生争议的责任","2020版教材P292页 《建设工程价款结算暂行办法》第十四条中规定：发包人要求承包人完成合同以外零星项目，承包人应在接受发包人要求的7天内就用工数量和单价、机械台班数量和单价、使用材料和金额等向发包人提出施工签证，发包人签证后施工，如发包人未签证，承包人施工后发生争议的，责任由承包人自负。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]