[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1115604":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1115604,788,1,"单选题","某工程项目需要进行试生产，其配套的环境保护设施的竣工验收应该（）进行。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","由生产单位试生产3个月后向审批环境影响评价文件的环境保护行政主管部门申请验收",false,{"key":16,"text":17,"correct":14},"B","由建设单位自主体工程竣工验收合格之日起3个月内向审批环境影响评价文件的环境保护行政主管部门申请验收",{"key":19,"text":20,"correct":21},"C","编制环境影响报告书、环境影响报告表的建设项目竣工后，建设单位应当按照国务院环境保护行政主管部门规定的标准和程序，对配套建设的环境保护设施进行验收",true,{"key":23,"text":24,"correct":14},"D","由建设单位组织试生产3个月后，向审批环境影响评价文件的环境保护行政主管部门申请验收","2020版教材P288页 编制环境影响报告书、环境影响报告表的建设项目竣工后，建设单位应当按照国务院环境保护行政主管部门规定的标准和程序，对配套建设的环境保护设施进行验收，编制验收报告。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]