[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1115590":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1115590,788,1,"单选题","关于工程竣工验收，下列表述错误的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","完成建设工程设计和合同约定的各项内容的工程，才能进行竣工验收",false,{"key":16,"text":17,"correct":14},"B","建设工程未经规划验收核实或经核实不符合规划条件的，不得组织竣工验收",{"key":19,"text":20,"correct":21},"C","依法应进行消防验收的工程，未经消防验收或消防验收不合格的，不得组织竣工验收",true,{"key":23,"text":24,"correct":14},"D","环境保护设施竣工验收，应当与主体工程竣工验收同时进行","2020版教材P288页 依法应当进行消防验收的建设工程，未经消防验收或者消防验收不合格的，禁止投入使用；其他建设工程经依法抽查不合格的，应当停止使用。未规定消防验收对工程竣工验收的制约关系。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]