[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1115584":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1115584,788,1,"单选题","建设单位在工程招标及与勘察、设计、施工、监理等单位签订合同时，应对工程文件的套数、费用、质量、移交时间等提出明确要求。勘察、设计、施工、监理等单位应将本单位形成的工程文件立卷后()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","向建设行政主管部门移交",false,{"key":16,"text":17,"correct":14},"B","向城建档案馆移交",{"key":19,"text":20,"correct":21},"C","向建设单位移交",true,{"key":23,"text":24,"correct":14},"D","通过建设单位转交","2020版教材P287页 建设单位是工程建设活动的总负责方，应当在合同中明确要求勘察、设计、施工、监理等单位分别提供工程建设各环节的文件资料，及时收集整理，建立健全建设项目档案。即勘察、设计、施工、监理等单位应将本单位形成的工程文件立卷后向建设单位移交。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]