[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1115580":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1115580,788,1,"单选题","由于建筑材料价格上涨导致承包人索赔，根据计价方式的不同，对于该索赔不予支持的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","可调价",false,{"key":16,"text":17,"correct":14},"B","成本价酬金",{"key":19,"text":20,"correct":21},"C","固定价",true,{"key":23,"text":24,"correct":14},"D","总价","2020版教材P293页 2004年10月发布的《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释》第16条规定，当事人对建设工程的计价标准或者计价方法有约定的，按照约定结算工程价款。只能在约定C固定价的提前下不予支持。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]