[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1115563":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1115563,788,1,"单选题","进场的建筑材料、建筑构配件和设备在使用或者安装前，应该经过（）签字。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理工程师",true,{"key":16,"text":17,"correct":18},"B","总监理工程师",false,{"key":20,"text":21,"correct":18},"C","项目经理",{"key":23,"text":24,"correct":18},"D","建设单位代表","2020版教材P283页 未经监理工程师签字，建筑材料、建筑构配件和设备不得在工程上使用或者安装，施工单位不得进行下一道工序的施工。未经总监理工程师签字，建设单位不拨付工程款，不进行竣工验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]