[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1115533":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1115533,788,1,"单选题","对于按照合同约定由建设单位采购运抵现场的墙体材料、门窗、保温材料、采暖制冷和照明设备等，施工单位应当()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","直接使用和安装",false,{"key":16,"text":17,"correct":18},"B","进行检验并经监理签字后再使用和安装",true,{"key":20,"text":21,"correct":14},"C","在供货商出具产品合格证后使用和安装",{"key":23,"text":24,"correct":14},"D","按建设单位的指示使用和安装","2020版教材P283页 未经监理工程师签字，建筑材料、建筑构配件和设备不得在工程上使用或者安装，施工单位不得进行下一道工序的施工。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]