[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1115525":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1115525,788,1,"单选题","根据《建设工程质量管理条例》，下列不属于施工企业进行施工的依据为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程监理合同",true,{"key":16,"text":17,"correct":18},"B","施工合同中约定采用的推荐性标准",false,{"key":20,"text":21,"correct":18},"C","建筑法律",{"key":23,"text":24,"correct":18},"D","施工图设计文件","2020版教材P269页 《建筑法》规定，建筑施工企业必须按照工程设计图纸和施工技术标准施工，不得偷工减料。施工单位只有按照施工技术标准，特别是强制性标准的要求施工，才能保证工程的施工质量",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]