[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1115524":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1115524,788,1,"单选题","具有总承包一级资质的某企业与甲工程的施工总承包签订合同后，建设单位同意将网架工程分包给具有相应资质等级的另一施工企业，按照我国《建设工程质量管理条例》的要求，某企业应确定甲工程项目的（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目经理、分包方项目经理和施工管理负责人",false,{"key":16,"text":17,"correct":18},"B","项目经理、技术负责人和施工管理负责人",true,{"key":20,"text":21,"correct":14},"C","项目经理、技术负责人、分包方项目经理和技术负责人",{"key":23,"text":24,"correct":14},"D","项目经理、技术负责人和分包项目安全负责人","2020版教材P267页 《建筑法》规定，建筑施工企业对工程的施工质量负责。《建设工程质量管理条例》进一步规定，施工单位对建设工程的施工质量负责。施工单位应当建立质量责任制，确定工程项目的项目经理、技术负责人和施工管理负责人。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]