[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1115497":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1115497,788,1,"单选题","某施工单位地下室柱子钢筋绑扎完成，准备浇注混凝土时，按照《建设工程质量管理条例》要求，施工单位应通知建设单位和()参加隐蔽验收。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设行政主管部门",false,{"key":16,"text":17,"correct":14},"B","设计单位",{"key":19,"text":20,"correct":21},"C","建设工程质量监督机构",true,{"key":23,"text":24,"correct":14},"D","勘察单位","2020版教材P271页 《建设工程质量管理条例》规定，施工单位必须建立、健全施工质量的检验制度，严格工序管理，作好隐蔽工程的质量检查和记录。隐蔽工程在隐蔽前，施工单位应当通知建设单位和建设工程质量监督机构。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]