[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1115472":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1115472,788,1,"单选题","政府对工程质量的监督管理的主要手段为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计审批制度和竣工验收备案制度",false,{"key":16,"text":17,"correct":18},"B","施工许可制度和竣工验收备案制度",true,{"key":20,"text":21,"correct":14},"C","设计审批制度和施工许可制度",{"key":23,"text":24,"correct":14},"D","设计审批制度、用地审批制度和竣工验收备案制度","2020版教材P264页 建设项目规划审查机构应当对工程建设规划阶段执行强制性标准的情况实施监督。施工图设计文件审查单位应当对工程建设勘察、设计阶段执行强制性标准的情况实施监督。建筑安全监督管理机构应当对工程建设施工阶段执行施工安全强制性标准的情况实施监督。工程质量监督机构应当对工程建设施工、监理、验收等阶段执行强制性标准的情况实施监督。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]