[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1115443":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1115443,788,1,"单选题","建设单位要求施工单位压缩合同约定的工期的，最轻的处罚是责令限期改正，并处（）的罚款。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2万元以上10万元以下",false,{"key":16,"text":17,"correct":14},"B","10万元以上20万元以下",{"key":19,"text":20,"correct":21},"C","20万元以上50万元以下",true,{"key":23,"text":24,"correct":14},"D","50万元以上","2020版教材P251页 建设单位有下列行为之一的责令限期改正，处20万元以上50万元以下的罚款。1）对勘察、设计、施工、工程监理等单位提出不符合安全生产法律、法规和强制性标准规定的要求的2）要求施工单位压缩合同约定的工期的3）将拆除工程发包给不具有相应资质等级的施工单位的。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]