[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1115420":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1115420,788,1,"单选题","某建设单位不按合同约定，要求施工单位压缩工期。为此，该建设单位应承担的法律责任是：限期改正，并处一定额度的罚款。该罚款额度是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","10万元以下",false,{"key":16,"text":17,"correct":14},"B","10万元以上20万元以下",{"key":19,"text":20,"correct":14},"C","50万元以上",{"key":22,"text":23,"correct":24},"D","20万元以上50万元以下",true,"2020版教材P251页 建设单位有下列行为之一的，责令限期改正，处20万元以上50万元以下的罚款；造成重大安全事故，构成犯罪的，对直接责任人员，依照刑法有关规定追究刑事责任；造成损失的，依法承担赔偿责任：要求施工单位压缩合同约定的工期的。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]