[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1115286":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1115286,788,1,"单选题","项目负责人每月带班生产时间最低为本月施工时间的()%。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","50",false,{"key":16,"text":17,"correct":14},"B","60",{"key":19,"text":20,"correct":14},"C","75",{"key":22,"text":23,"correct":24},"D","80",true,"2020版教材P209页 二、施工单位项目负责人施工现场带班制度。项目负责人每月带班生产时间不得少于本月施工时间的80%，因其他事务需离开施工现场时，应向工程项目的建设单位请假，经批准后方可离开。离开期间应委托项目相关负责人负责其外出时的日常工作。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]