[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1115213":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1115213,788,1,"单选题","某建筑施工企业在2013年5月仍在持2010年1月1日办理的安全生产许可证进行施工，受到有关部门查处。该案的正确处理方式是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","允许其继续施工，限期补办延期手续",false,{"key":16,"text":17,"correct":14},"B","允许其继续施工，但处以50万元罚款",{"key":19,"text":20,"correct":21},"C","责令停止施工，限期补办延期手续，没收违法所得，并处以5万元以上10万元以下罚款",true,{"key":23,"text":24,"correct":14},"D","责令停业整顿，限期补办延期手续，并处以10万元以上50万元以下罚款","2020版教材P203页 安全生产许可证有效期满未办理延期手续，继续进行生产的，责令停止生产，限期补办延期手续，没收违法所得，并处以5万元以上10万元以下罚款。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]