[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114920":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1114920,788,1,"单选题","某工程总承包商将土方工程分包给了甲分包商，将基础工程分包给了乙分包商。在施工合同履行中，甲分包商延误了工期。对此，乙分包商提出要求承担违约责任的对象是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包方",false,{"key":16,"text":17,"correct":18},"B","总承包商",true,{"key":20,"text":21,"correct":14},"C","甲分包商",{"key":23,"text":24,"correct":14},"D","监理单位","2020版教材P126 ：由于承担违约责任的前提是要有有效的合同，与乙分包商有合同关系的只有总承包商，并且《民法典》第121条规定“当事人一方因第三人原因造成违约的，应当向对方承担违约责任”，本题的第三人是甲分包商，当事人一方是总承包商，现由于甲分包商违约，承担违约责任的自然就应该是总承包商。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]